Global Dietary Supplement Company

May 20, 2021

Touchstone Engineers led onsite commissioning of the renovated data center, originally built for Dell.  Equipment included Duke Energy leased and controlled Caterpillar 1.5MW standby generator, PLC-controlled utility/generator transfer switchgear, 2N redundant Liebert 675kW UPS systems, AHUs, and an EPO system.